[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896962":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},896962,581,1,"单选题","某项目招标，经评标委员会评审认为所有投标都不符合招标文件的要求，这时应当（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","与相对接近要求的投标人协商，改为议标确定中标人",false,{"key":16,"text":17,"correct":14},"B","改为直接发包",{"key":19,"text":20,"correct":14},"C","用原招标文件重新招标",{"key":22,"text":23,"correct":24},"D","修改招标文件后重新招标",true,"本题考查的是招标投标法实施条例。经评标委员会评审认为所有投标都不符合招标文件的要求，应当修改招标文件后重新招标。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]