[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896942":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},896942,581,1,"单选题","建设工程项目管理的核心任务是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","控制项目采购",false,{"key":16,"text":17,"correct":18},"B","控制项目目标",true,{"key":20,"text":21,"correct":14},"C","控制项目风险",{"key":23,"text":24,"correct":14},"D","控制项目信息","工程项目管理的核心是控制项目基本目标(质量、造价、进度），最终实现项目功能，以满足项目使用者及利益相关者需求。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]