[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896876":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},896876,581,1,"单选题","间接成本是指与研制开发有关的费用，其中不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","非专用设备折旧费",false,{"key":16,"text":17,"correct":14},"B","管理费",{"key":19,"text":20,"correct":14},"C","应分摊的公共费用及能源费用",{"key":22,"text":23,"correct":24},"D","咨询鉴定费",true,"研制成本包括直接成本和间接成本：直接成本是指研制过程中直接投入发生的费用(主要包括材料费用、工资费用、专用设备费、资料费、咨询鉴定费、协作费、培训费和差旅费等)，间接成本是指与研制开发有关的费用(主要包括管理费、非专用设备折旧费、应分摊的公共费用及能源费用)。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]