[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896872":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},896872,581,1,"单选题","新增固定资产价值是建设项目竣工投产后所增加的固定资产的价值，它是以（ ）形态表示的固定资产投资最终成果的综合性指标。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","时间",false,{"key":16,"text":17,"correct":14},"B","期货",{"key":19,"text":20,"correct":14},"C","货币",{"key":22,"text":23,"correct":24},"D","价值",true,"新增固定资产价值是建设项目竣工投产后所增加的固定资产的价值，它是以价值形态表示的固定资产投资最终成果的综合性指标。新增固定资产价值是投资项目竣工投产后所增加的固定资产价值，即交付使用的固定资产价值，是以价值形态表示建设项目的固定资产最终成果的指标。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]