[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896864":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},896864,581,1,"单选题","完整的竣工决算书包含的内容是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","竣工财务决算说明书、竣工财务决算报表、工程竣工图、工程竣工造价对比分析",true,{"key":16,"text":17,"correct":18},"B","竣工财务决算报表、竣工决算、工程竣工图、工程造价对比分析",false,{"key":20,"text":21,"correct":18},"C","竣工财务决算说明书、竣工决算、竣工验收报告、工程造价对比分析",{"key":23,"text":24,"correct":18},"D","竣工财务决算报表、工程竣工图、工程造价对比分析","按照财政部、国家发改委和住房城乡建设部的有关文件规定，竣工决算由竣工财务决算说明书、竣工财务决算报表、工程竣工图和工程竣工造价对比分析四部分组成。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]