[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896861":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},896861,581,1,"单选题","根据《建设工程价款结算暂行办法》的规定，在竣工结算编审过程中，单位工程竣工结算的编制人是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","业主",false,{"key":16,"text":17,"correct":18},"B","承包商",true,{"key":20,"text":21,"correct":14},"C","总承包商",{"key":23,"text":24,"correct":14},"D","监理咨询机构","单位工程竣工结算由承包人编制，发包人审查;实行总承包的工程，由具体承包人编制，在总包人审查的基础上，发包人审查。单项工程竣工结算或建设项目竣工总结算由总(承)包人编制，发包人可直接进行审查，也可以委托具有相应资质的工程造价咨询机构进行审查。政府投资项目由同级财政部门审查。单项工程竣工结算或建设项目竣工总结算经发包人、承包人签字盖章后有效。承包人应在合同约定期限内完成项目竣工结算编制工作，未在规定期限内完成的，并且提不出正当理由延期的，责任自负。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]