[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896857":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},896857,581,1,"单选题","按合同约定扣回预付款，下列说法不正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","付款的扣款方法由发包人和承包人通过洽商后在合同中予以确定",false,{"key":16,"text":17,"correct":18},"B","一般是在承包人完成金额累计达到合同总价的一定比例后，由发包人开始向承包人还款",true,{"key":20,"text":21,"correct":14},"C","发包方从每次应付给承包人的金额中扣回工程预付款",{"key":23,"text":24,"correct":14},"D","发包人至少在合同规定的完工期前将工程预付款的总金额逐次扣回","预付款的扣款方法由发包人和承包人通过洽商后在合同中予以确定，一般是在承包人完成额累计达到合同总价的一定比例后，由承包人开始向发包人还款，发包方从每次应付给承包人的金额中扣回工程预付款，发包人至少在合同规定的完工期前将工程预付款的总金额逐次扣回。国际工程中的扣款方法一般为：当工程进度款累计金额超过合同价格的10%-20%时开始起扣，每月从进度款中按一定比例扣回。考前黑钻押题，金考典软件考前更新，下载链接 www.jinkaodian.com",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]