[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896853":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},896853,581,1,"单选题","已知某工程承包合同价款总额是3000万元，其主要材料及构件所占比重为60%，预付款总金额为工程价款总额的20%，则预付款起扣点是（ ）万元。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","1000",false,{"key":16,"text":17,"correct":14},"B","1400",{"key":19,"text":20,"correct":14},"C","1500",{"key":22,"text":23,"correct":24},"D","2000",true,"起扣点的计算公式如下：T=P-M\u002FN 式中T一一起扣点(即工程预付款开始扣回时)的累计完成工程金额；P一一承包工程合同总额；M一一工程预付款总额； N一一主要材料及构件所占比重。 预付款起扣点=3000-(3000×20%)÷60%=2000万元。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]