[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896850":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},896850,581,1,"单选题","施工单位在施工中发生如下事项：完成业主要求的合同外用工花费3万元；由于设计图纸延误造成工人窝工损失1万元；施工电梯机械故障造成工人窝工损失2万元。施工单位可向业主索赔的人工费为（ ）万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","3",false,{"key":16,"text":17,"correct":14},"B","5",{"key":19,"text":20,"correct":21},"C","4",true,{"key":23,"text":24,"correct":14},"D","6","施工单位可向业主索赔的人工费为(3+1)万元=4万元。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]