[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896849":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},896849,581,1,"单选题","关于工期索赔，下列说法不正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","因承包人的原因造成施工进度滞后，属于不可原谅的延期",false,{"key":16,"text":17,"correct":18},"B","只有发包人不应承担任何责任的延误，才是可原谅的延期",true,{"key":20,"text":21,"correct":14},"C","只有位于关键线路上工作内容的滞后，才会影响到竣工日期",{"key":23,"text":24,"correct":14},"D","只有可原谅延期部分才能批准顺延合同工期","因承包人的原因造成施工进度滞后，属于不可原谅的延期；只有承包人不应承担任何责任的延误，才是可原谅的延期。有时工程延期的原因中可能包含有双方责任，此时工程师应进行详细分析，分清责任比例，只有可原谅延期部分才能批准顺延合同工期。只有位于关键线路上工作内容的滞后，才会影响到竣工日期。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]