[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896846":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},896846,581,1,"单选题","就施工索赔的目的而言，施工索赔包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","物价上涨索赔和业主违约索赔",false,{"key":16,"text":17,"correct":18},"B","工期索赔和费用索赔",true,{"key":20,"text":21,"correct":14},"C","拖延付款索赔和不可抗拒因素索赔",{"key":23,"text":24,"correct":14},"D","特殊风险索赔和业主风险索赔","工程索赔按不同的划分标准，可分为不同类型。按索赔目的分类，工程索赔分为工期索赔和费用索赔。按索赔的合同依据分类，工程索赔可分为合同中明示的索赔和合同中默示的索赔。根据索赔事件的性质不同，可以将工程索赔分为： (1)工程延误索赔。 (2)工程变更索赔。 (3)合同被迫终止的索赔。 (4)赶工索赔。 (5)意外风险和不可预见因素索赔。 (6)其他索赔。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]