[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896844":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},896844,581,1,"单选题","下列索赔费用中，不属于材料费的索赔的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","由于索赔事件的发生造成材料实际用量超过计划用量而增加的材料费",false,{"key":16,"text":17,"correct":14},"B","由于发包人原因导致工程延期期间的材料价格上涨和超期储存费用",{"key":19,"text":20,"correct":14},"C","运输费，仓储费，以及合理的损耗费用",{"key":22,"text":23,"correct":24},"D","由于承包商管理不善，造成材料损坏失效",true,"材料费的索赔包括：由于索赔事件的发生造成材料实际用量超过计划用量而增加的材料费，由于发包人原因导致工程延期期间的材料价格上涨和超期储存费用。材料费中应包括运输费、仓储费以及合理的损耗费用。如果由于承包商管理不善造成材料损坏、失效，则不能列入索赔款项内 。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]