[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896843":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},896843,581,1,"单选题","根据《建设工程施工合同示范文本》中的合同条款，关于合理补偿承包人索赔的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承包人遇到不利物质条件可进行利润索赔",false,{"key":16,"text":17,"correct":18},"B","发生不可抗力只能进行工期索赔",true,{"key":20,"text":21,"correct":14},"C","异常恶劣天气导致的停工通常可以进行费用索赔",{"key":23,"text":24,"correct":14},"D","发包人原因引起的暂停施工只能进行工期索赔","",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]