[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896840":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},896840,581,1,"单选题","实现成本目标责任制的保证和手段是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","成本考核",true,{"key":16,"text":17,"correct":18},"B","成本分析",false,{"key":20,"text":21,"correct":18},"C","成本控制",{"key":23,"text":24,"correct":18},"D","成本计划","成本测算是指编制投标报价时对预计完成该合同施工成本的测算；它是决定最终投标价格取定的核心数据。成本测算数据是成本计划的编制基础，成本计划是开展成本控制和核算的基础；成本控制能对成本计划的实施进行监督，保证成本计划的实现，而成本核算又是成本计划是否实现的最后检查，成本核算所提供的成本信息又是成本分析、成本考核的依据；成本分析为成本考核提供依据，也为未来的成本测算与成本计划指明方向；成本考核是实现成本目标责任制的保证和手段。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]