[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896838":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},896838,581,1,"单选题","项目成本计划的编制方法中，当项目非常庞大和复杂而需要分为几个部分时，可采用（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","定率估算法",true,{"key":16,"text":17,"correct":18},"B","技术进步法",false,{"key":20,"text":21,"correct":18},"C","按实计算法",{"key":23,"text":24,"correct":18},"D","目标利润法","定率估算法(历史资料法) 。当工程项目非常庞大和复杂而需要分为几个部分时采用的方法。首先将工程项目分为若干子项目，参照同类工程项目的历史数据，采用算术平均法计算子项目目标成本降低率和降低额，然后再汇总整个工程项目的目标成本降低率、降低额。在确定子项目成本降低率时，可采用加权平均法或三点估算法。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]