[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896837":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},896837,581,1,"单选题","建设工程成本管理内容中，（ ）是目标成本的一种表达形式，是建立项目成本管理责任制、开展成本控制和核算的基础，是进行成本费用控制的主要依据。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","成本分析",false,{"key":16,"text":17,"correct":18},"B","成本计划",true,{"key":20,"text":21,"correct":14},"C","成本控制",{"key":23,"text":24,"correct":14},"D","成本核算","成本计划是在成本预测的基础上，施工承包单位及其项目经理部对计划期内工程项目成本水平所做的筹划。施工成本计划是以货币形式表达的项目在计划期内的生产费用、成本水平及为降低成本采取的主要措施和规划的具体方案。成本计划是目标成本的一种表达形式，是建立项目成本管理责任制、开展成本控制和核算的基础，是进行成本费用控制的主要依据。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]