[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896835":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},896835,581,1,"单选题","项目经理部可控责任成本考核指标不包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目经理责任目标总成本降低额和降低率",false,{"key":16,"text":17,"correct":14},"B","施工计划成本实际降低额和降低率",{"key":19,"text":20,"correct":21},"C","设计成本降低额和降低率",true,{"key":23,"text":24,"correct":14},"D","施工责任目标成本实际降低额和降低率","项目经理部可控责任成本考核指标： ①项目经理责任目标总成本降低额和降低率。 ②施工责任目标成本实际降低额和降低率。 ③施工计划成本实际降低额和降低率。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]