[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896833":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},896833,581,1,"单选题","成本控制方法中，（ ）是对工程项目成本\u002F进度进行综合控制的一种分析方法。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工期一成本同步分析法",false,{"key":16,"text":17,"correct":18},"B","挣值法",true,{"key":20,"text":21,"correct":14},"C","项目成本分析表法",{"key":23,"text":24,"correct":14},"D","比率法","赢得值法也叫挣值法。赢得值法是对工程项目成本\u002F进度进行综合控制的一种分析方法。通过比较已完工程预算成本与已完工程实际成本之间的差值，可以分析由于实际价格的变化而引起的累计成本偏差；通过比较已完工程预算成本与拟完工程预算成本之间的差值，可以分析由于进度偏差而引起的累计成本偏差。并通过计算后续未完工程的计划成本余额，预测其尚需的成本数额，从而为后续工程施工的成本、进度控制及寻求降低成本途径指明方向。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]