[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896830":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},896830,581,1,"单选题","根据《建设工程工程量清单计价规范》（GB50500-2013），关于施工发承包投标报价的编制，下列做法正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","A.设计图纸与招标工程量清单项目特征描述不同的，以设计图纸特征为准",false,{"key":16,"text":17,"correct":18},"B","暂列金额应按照招标工程量清单中列出的金额填写，不得变动以后发生的为准，以招标工程量清单为准",true,{"key":20,"text":21,"correct":14},"C","材料、工程设备暂估价应按暂估单价，乘以所需数量后计入其他项目费",{"key":23,"text":24,"correct":14},"D","总承包服务费应按照投标人提出的协调、配合和服务项目自主报价","本题考查的是投标报价编制。设计图纸与招标工程量清单项目特征描述不同的，以招标工程量清单特征为准。材料、工程设备暂估价应按暂估单价应计入分部分项工程量清单综合单价当中。总承包服务费应按照招标人提出的协调、配合和服务项目自主报价。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]