[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896823":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},896823,581,1,"单选题","建设工程施工投标报价程序中，确定基础标价的紧后工作是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","标书编制",false,{"key":16,"text":17,"correct":18},"B","选择报价策略调整标价",true,{"key":20,"text":21,"correct":14},"C","招标文件研究",{"key":23,"text":24,"correct":14},"D","计算投标报价","建设工程施工投标报价程序中，确定基础标价的紧后工作是选择报价策略调整标价。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]