[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896821":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},896821,581,1,"单选题","关于招标控制价的相关规定，下列说法中正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","国有资金投资的工程建设项目，应编制招标控制价",true,{"key":16,"text":17,"correct":18},"B","招标控制价应在招标文件中公布，仅需公布总价",false,{"key":20,"text":21,"correct":18},"C","招标控制价超过批准概算3%以内时，招标人不必将其报原概算审批部门审核",{"key":23,"text":24,"correct":18},"D","当招标控制价复查结论超过原公布的招标控制价3%以内时，应责成招标人改正","本题考查的是最高投标限价的编制。招标控制价应在招标文件中公布，需公布总价以外，还要公布各单位工程的分部分项工程费、措施项目费、其他项目费、规费以及增值税。招标控制价只要超过批准概算，招标人应将其报原概算审批部门审核。当招标控制价复查结论超过原公布的招标控制价3%以外时，应责成招标人改正。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]