[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896816":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},896816,581,1,"单选题","编制工程量清单时，招标人自行供应材料、工程设备的，总承包服务费按招标人供应材料、工程设备价值的（ ）计算。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1%",true,{"key":16,"text":17,"correct":18},"B","1．5%",false,{"key":20,"text":21,"correct":18},"C","3%",{"key":23,"text":24,"correct":18},"D","5%","编制最高投标限价时，总承包服务费应按照省级或行业建设主管部门的规定计算，或者根据行业经验标准计算。针对一般情况，可参考的常用标准如下： 1)招标人仅要求对分包的专业工程进行总承包管理和协调时，按分包的专业工程估算造价的1.5%计算。 2)招标人要求对分包的专业工程进行总承包管理和协调，并同时要求提供配合服务时，根据招标文件中列出的配合服务内容和提出的要求，按分包的专业工程估算造价的3%~5%计算。 3)招标人自行供应材料、工程设备的，按招标人供应材料、工程设备价值的1%计算。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]