[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896815":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},896815,581,1,"单选题","投标人经复核认为招标人公布的招标控制价未按照规定进行编制的，应在招标控制价公布后（ ）天向招标投标监督机构或工程造价管理机构投诉。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5",true,{"key":16,"text":17,"correct":18},"B","10",false,{"key":20,"text":21,"correct":18},"C","15",{"key":23,"text":24,"correct":18},"D","20","最高投标限价，又称招标控制价，是招标人根据国家或省级、行业建设主管部门颁发的有关计价依据和办法，依据拟订的招标文件和招标工程量清单，结合工程具体情况发布的对投标人的投标报价进行控制的最高价格。投标人经复核认为招标人公布的最高投标限价未按照 《 建设工程工程量清单计价规范 》GB50500-2013的规定进行编制的，应在最高投标限价公布后5天内向招标投标监督机构和工程造价管理机构投诉 。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]