[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896807":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},896807,581,1,"单选题","根据《建设工程工程量清单计价规范》（GB50500-2013），关于工程量清单计价的有关要求，下列说法中正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","事业单位自有资金投资的建设工程发承包，可以不采用工程量清单计价",false,{"key":16,"text":17,"correct":18},"B","使用国有资金投资的建设工程发承包，必须采用工程量清单计价",true,{"key":20,"text":21,"correct":14},"C","国有资金投资总额占40%以上的项目，必须采用工程量清单计价",{"key":23,"text":24,"correct":14},"D","招标工程量清单的准确性和完整性由清单编制人负责","本题考查的是工程量清单编制。事业单位自有资金投资的建设工程发承包，必须采用工程量清单计价；国有资金投资总额占50%以上的项目，必须采用工程量清单计价；招标工程量清单的准确性和完整性由招标人负责。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]