[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896805":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},896805,581,1,"单选题","根据《建设工程工程量清单计价规范》（GB50500-2013），一般不作为安全文明施工费计算基础的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","定额人工费",false,{"key":16,"text":17,"correct":18},"B","定额人工费＋定额材料费",true,{"key":20,"text":21,"correct":14},"C","定额人工费＋定额施工机具使用费",{"key":23,"text":24,"correct":14},"D","定额人工费＋定额材料费＋定额施工机具使用费","本题考查的是工程量清单编制。“计算基础”中安全文明施工费可为“定额基价”、“定额人工费”或“定额人工费+定额施工机具使用费”，其他项目可为“定额人工费”或“定额人工费+定额施工机具使用费”",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]