[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896792":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},896792,581,1,"单选题","某工程合同价为 300 万元， 本期完成合同价款 100 万元， 合同约定： 采用调值公式进行动态结算， 其中固定要素比重为 0.2， 调价要素分为 A、 B、 C 三类， 分别占合同价的比重为 0.15、 0.35、 0.3， 结算时价格指数分别增长了 20%、 15%、 25%， 则该工程需要调整的价款差额为（ ） 万元",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","115.75",false,{"key":16,"text":17,"correct":14},"B","19.75",{"key":19,"text":20,"correct":21},"C","15.75",true,{"key":23,"text":24,"correct":14},"D","120.75","100×[0.2+（0.15×1.2+0.35×1.15+0.3×1.25） -1]=15.75 万元",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]