[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896788":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},896788,581,1,"单选题","关于施工承包合同中缺陷责任与保修的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","缺陷责任期自实际竣工日期起计算，最长不超过12个月",false,{"key":16,"text":17,"correct":18},"B","由他人原因造成的缺陷，发包人负责组织维修，承包人不承担费用，且发包人不得从保证金中扣除费用",true,{"key":20,"text":21,"correct":14},"C","因发包人原因导致工程无法按合同约定期限进行竣工验收的，缺陷责任期自竣工验收合格之日开始计算",{"key":23,"text":24,"correct":14},"D","发包人未经竣工验收擅自使用工程的，缺陷责任期自承包人提交竣工验收申请报告之日开始计算","本题考查的是施工合同示范文本。缺陷责任期自通过竣工验收之日起计算，最长不超过24个月。因发包人原因导致工程无法按合同约定期限进行竣工验收的，承包人提交竣工验收报告90天后，工程自动进行缺陷责任期。发包人未经竣工验收擅自使用工程的，缺陷责任期自转移占有之日开始计算。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]