[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896780":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},896780,581,1,"单选题","由于发包人原因导致工程无法按规定期限竣(交)工验收的，在承包人提交竣(交)工验收报告（ ）天后，工程自动进入缺陷责任期。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","30",false,{"key":16,"text":17,"correct":14},"B","60",{"key":19,"text":20,"correct":21},"C","90",true,{"key":23,"text":24,"correct":14},"D","120","因发包人原因导致工程无法按合同约定期限进行竣工验收的，在承包人提交竣工验收报告90天后，工程自动进入缺陷责任期；发包人未经竣工验收擅自使用工程的，缺陷责任期自工程转移占有之日起开始计算。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]