[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896774":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},896774,581,1,"单选题","根据《建设工程价款结算暂行办法》，在具备施工条件的前提下，发包人支付预付款的期限应是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","不迟于约定的开工日期前的7天内",true,{"key":16,"text":17,"correct":18},"B","不迟于约定的开工日期后的7天内",false,{"key":20,"text":21,"correct":18},"C","不迟于约定的开工日期前的14天内",{"key":23,"text":24,"correct":18},"D","不迟于约定的开工日期后的14天内","预付款的支付按照专用合同条款约定执行，但至迟应在开工通知载明的开工日期7天前支付。预付款应当用于材料、工程设备、施工设备的采购及修建临时工程、组织施工队伍进场等。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]