[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896771":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},896771,581,1,"单选题","根据我国《建设工程质量保证金管理暂行办法》有关规定，下列表述中错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","缺陷责任期从工程通过竣(交)工验收之日起计算",false,{"key":16,"text":17,"correct":14},"B","由于发包人原因导致工程无法按规定期限进行竣(交)工验收的，在承包人提交竣(交)工验收报告90天后，工程自动进入缺陷责任期",{"key":19,"text":20,"correct":21},"C","全部或部分使用政府投资的建设项目，保证金按工程价款结算总额的3%预留",true,{"key":23,"text":24,"correct":14},"D","缺陷责任期内，承包人维修并承担相应费用后，不免除对工程的一般损失赔偿责任","缺陷责任期从工程通过竣工验收之日起计算，合同当事人应在专用合同条款约定缺陷责任期的具体期限，但该期限最长不超过24个月。发包人累计扣留的质量保证金不得超过工程价款结算总额的3%。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]