[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896760":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},896760,581,1,"单选题","当建设工程条件相同时，用同类已完工程的预算或未完但已经过审查修正的工程预算审查拟建工程的方法是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","标准预算审查法",false,{"key":16,"text":17,"correct":18},"B","对比审查法",true,{"key":20,"text":21,"correct":14},"C","筛选审查法",{"key":23,"text":24,"correct":14},"D","全面审查法","本题考查的是施工图预算的编制。对比审查法是用已建工程的预算或虽未建成但已通过审查的工程预算，对比审查拟建工程预算的一种方法。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]