[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896754":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},896754,581,1,"单选题","有关费用项目计取的审查要注意的方面不包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","措施费的计算是否符合有关的规定标准",false,{"key":16,"text":17,"correct":18},"B","直接费和利润的计取基础是否符合现行规定",true,{"key":20,"text":21,"correct":14},"C","有无巧立名目，乱计费、乱摊费用现象",{"key":23,"text":24,"correct":14},"D","预算外调增的材料差价是否计取了企业管理费","有关费用项目计取的审查要注意以下几个方面： (1)措施费的计算是否符合有关的规定标准，企业管理费和利润的计取基础是否符合现行规定，有无不能作为计费基础的费用列入计费的基础。 (2)预算外调增的材料差价是否计取了企业管理费。人工费增减后，有关费用是否相应做了调整 。 (3)有无巧立名目，乱计费、乱摊费用现象。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]