[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896752":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},896752,581,1,"单选题","适应市场经济条件的工程量清单计价模式下的施工图预算编制方法是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","实物量法",false,{"key":16,"text":17,"correct":14},"B","可调单价法",{"key":19,"text":20,"correct":21},"C","综合单价法",true,{"key":23,"text":24,"correct":14},"D","工料单价法","施工图预算的编制可以采用工料单价法和综合单价法。工料单价法是指分部分项工程的工料机单价，以分部分项工程量乘以对应工料单价汇总后另加企业管理费、利润、税金生成单位工程施工图预算造价。按照分部分项工程单价产生的方法不同，工料单价法又可以分为预算单价法和实物量法。而综合单价法是适应市场经济条件的工程量清单计价模式下的施工图预算编制方法。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]