[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896751":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},896751,581,1,"单选题","当初步设计深度较深、有详细的设备清单时，最能精确地编制设备安装工程费概算的方法是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","预算单价法",true,{"key":16,"text":17,"correct":18},"B","扩大单价法",false,{"key":20,"text":21,"correct":18},"C","设备价值百分比法",{"key":23,"text":24,"correct":18},"D","综合吨位指标法","本题考查的是设计概算的编制。设备安装工程概算的编制方法：最新题库，考前【黑钻押题】，金考典软件考前更新，下载链接 www.jinkaodian.com （1）预算单价法：初步设计较深，有详细设备清单时适用；（2）扩大单价法：初步设计深度不够、设备清单不完备，或仅有成套设备时适用。（3）设备价值百分比法：初步设计深度不够，只有设备出厂价。设备原价×安装费率适用于价格波动大不大的定型产品和通用产品。（4）综合吨位指标法：初步设计提供的设备清单有规格和设备重量时；适用于设备价格波动较大的非标准设备和引进设备的安装工程概算。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]