[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896741":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},896741,581,1,"单选题","对总概算投资超过批准投资估算（ ）以上的，应查明原因，重新上报审批。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","3%",false,{"key":16,"text":17,"correct":14},"B","5%",{"key":19,"text":20,"correct":14},"C","8%",{"key":22,"text":23,"correct":24},"D","10%",true,"审查建设规模(投资规模、生产能力等)、建设标准(用地指标、建筑标准等)、配套工程、设计定员等是否符合原批准的可行性研究报告或立项批文的标准。对总概算投资超过批准投资估算10%以上的，应查明原因，重新上报审批。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]