[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896739":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},896739,581,1,"单选题","设备安装工程费概算的编制方法中，（ ）常用于设备价格波动较大的非标准设备和引进设备的安装工程概算。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","预算单价法",false,{"key":16,"text":17,"correct":14},"B","设备价值百分率法",{"key":19,"text":20,"correct":14},"C","扩大单价法",{"key":22,"text":23,"correct":24},"D","综合吨位指标法",true,"当设计文件提供的设备清单有规格和设备重量时，可采用综合吨位指标编制概算，综合吨位指标由主管部门或由设计院根据已完类似工程资料确定。该法常用于设备价格波动较大的非标准设备和引进设备的安装工程概算，或者安装方式不确定，没有定额或指标。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]