[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896738":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},896738,581,1,"单选题","编制固定资产投资计划、确定和控制建设项目投资的依据是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","修正概算",false,{"key":16,"text":17,"correct":14},"B","施工图预算",{"key":19,"text":20,"correct":14},"C","投资估算",{"key":22,"text":23,"correct":24},"D","设计概算",true,"设计概算是编制固定资产投资计划，确定和控制建设项目投资的依据。国家规定，编制年度固定资产投资计划，确定计划投资总额及其构成数额，要以批准的初步设计概算为依据，没有批准的初步设计文件及其概算，建设工程就不能列入年度固定资产投资计划。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]