[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896736":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},896736,581,1,"单选题","设计概算的内容不包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","分部工程概算",true,{"key":16,"text":17,"correct":18},"B","单位工程概算",false,{"key":20,"text":21,"correct":18},"C","建设项目总概算",{"key":23,"text":24,"correct":18},"D","单项工程综合概算","设计概算可分单位工程概算、单项工程综合概算和建设项目总概算三级。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]