[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896731":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},896731,581,1,"单选题","审查设计概算的方法中，（ ）是对一些关键设备和设施、重要装置、引进工程图样不全、难以核算的较大投资进行多方查询核对，逐项落实的方法。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","对比分析法",false,{"key":16,"text":17,"correct":18},"B","查询核实法",true,{"key":20,"text":21,"correct":14},"C","设备价值百分率法",{"key":23,"text":24,"correct":14},"D","联合会审法","查询核实法是对一些关键设备和设施、重要装置、引进工程图纸不全、难以核算的较大投资进行多方查询核对，逐项落实的方法。主要设备的市场价向设备采购部门或招标公司查询核实，重要生产装置、设施向同类企业(工程)查询了解，引进设备价格及有关费税向进出口公司调查落实，复杂的建筑安装工程向同类工程的建设、承包、施工单位征求意见，深度不够或不清楚的问题直接同原概算编制人员、设计者询问清楚。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]