[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896712":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},896712,581,1,"单选题","可行性研究阶段建设项目投资估算原则上应采用（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","混合法",false,{"key":16,"text":17,"correct":18},"B","指标估算法",true,{"key":20,"text":21,"correct":14},"C","比例估算法",{"key":23,"text":24,"correct":14},"D","系数估算法","建设项目可行性研究阶段投资估算原则上应采用指标估算法。对投资有重大影响的主体工程应估算出分部分项工程量，参考相关概算指标或概算定额编制主要单项工程的投资估算。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]