[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896707":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},896707,581,1,"单选题","在可行性研究阶段，投资估算原则上应采用（ ）进行投资估算的编制。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","指标估算法",true,{"key":16,"text":17,"correct":18},"B","系数估算法",false,{"key":20,"text":21,"correct":18},"C","生产能力指数法",{"key":23,"text":24,"correct":18},"D","混合法","建设项目可行性研究阶段技资估算原则上应采用指标估算法。指标估算法是依据投资估算指标，对各单位工程或单项工程费用进行估算，进而估算建设项目总投资，再按相关规定估算工程建设其他费用、基本预备费、建设期利息等，形成拟建项目静态投资 。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]