[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896704":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},896704,581,1,"单选题","价差预备费一般根据国家规定的投资综合价格指数，按估算年份价格水平的投资额为基数，采用（ ）计算。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","复利方法",true,{"key":16,"text":17,"correct":18},"B","建设项目的工程费用乘以价差预备费率",false,{"key":20,"text":21,"correct":18},"C","工程建设其他费用乘以预备费率",{"key":23,"text":24,"correct":18},"D","以建设项目的工程费用和工程建设其他费用之和为基础，乘以预备费率","价差预备费的内容包括：人工、设备、材料、施工机械的价差费，建筑安装工程费及工程建设其他费用调整，利率、汇率调整等增加的费用。价差预备费一般根据国家规定的投资综合价格指数，按估算年份价格水平的投资额为基数，采用复利方法计算。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]