[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896701":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},896701,581,1,"单选题","下列投资估算方法中，适合于对估算精确度要求较高的方法是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","系数法",false,{"key":16,"text":17,"correct":18},"B","指标估算法",true,{"key":20,"text":21,"correct":14},"C","生产能力指数法",{"key":23,"text":24,"correct":14},"D","类似项目对比法","在可行性研究阶段，投资估算精度要求就要比前一阶段高些，需采用相对详细的估算方法，如指标估算法等。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]