[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896690":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},896690,581,1,"单选题","对于建筑设计因素对工业项目工程造价的影响，下列说法中正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建筑周长系数越高，建筑工程造价越低",false,{"key":16,"text":17,"correct":18},"B","多跨厂房跨度不变，中跨数目越多越经济",true,{"key":20,"text":21,"correct":14},"C","在建筑面积不变的情况下，建筑层高增加会引起各项费用的降低",{"key":23,"text":24,"correct":14},"D","建筑物层数越多，单位建筑面积的造价会降低","本题考查的是工程决策和设计阶段造价管理概述。多跨厂房，当跨度不变时，中跨数目越多越经济，因为柱子和基础分摊在单位面积上的造价减少。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]