[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896679":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},896679,581,1,"单选题","可行性研究报告的市场分析与预测不包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目建设基本条件",true,{"key":16,"text":17,"correct":18},"B","产品供需预测",false,{"key":20,"text":21,"correct":18},"C","市场现状调查",{"key":23,"text":24,"correct":18},"D","竞争力分析","市场分析与预测，包括市场预测内容、市场现状调查、产品供需预测、价格预测、竞争力分析、市场风险分析、市场调查与预测方法。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]