[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896675":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},896675,581,1,"单选题","BIM技术在施工过程中的应用包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","高效准确地估算出规划项目的总投资额",false,{"key":16,"text":17,"correct":14},"B","通过BIM技术对设计方案优选或限额设计",{"key":19,"text":20,"correct":14},"C","进行工程量自动计算、统计分析，形成准确的工程量清单",{"key":22,"text":23,"correct":24},"D","通过建筑信息模型确定不同时间节点的施工进度与施工成本",true,"本题考查的是BIM技术与工程造价。在施工之前就可以通过建筑信息模型确定不同时间节点的施工进度与施工成本，可以直观地按月、按周、按日观看到项目的具体实施情况并得到该时间节点的造价数据，方便项目的实时修改调整，实现限额领料施工；最大地体现造价控制的效果。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]