[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896672":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},896672,581,1,"单选题","分别反映各类工程的人工、材料、施工机械及主要设备报告期价格对基期价格的变化程度指标的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","月指数",false,{"key":16,"text":17,"correct":14},"B","综合造价指数",{"key":19,"text":20,"correct":21},"C","单项价格指数",true,{"key":23,"text":24,"correct":14},"D","时点造价指数","单项价格指数反映各类工程的人工费、材料费、施工机具使用费报告期价格对基期价格的变化程度的指标。可利用它研究主要单项价格变化的情况及其发展变化的趋势。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]