[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896653":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},896653,581,1,"单选题","在人工定额的损失时间里，工人在工作班内消耗的工作时间属于人工损失时间的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","休息时间",false,{"key":16,"text":17,"correct":18},"B","停工时间",true,{"key":20,"text":21,"correct":14},"C","不可避免的中断时间",{"key":23,"text":24,"correct":14},"D","准备与结束工作时间","损失时间是与产品生产无关，而与施工组织和技术上的缺点有关，最新题库，考前【黑钻押题】，金考典软件考前更新，下载链接 www.jinkaodian.com与工人在施工过程中的个人过失或某些偶然因素有关的时间消耗。包括： 1)多余和偶然工作时间； 2)停工时间； 3)违反劳动纪律的损失时间。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]