[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896651":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},896651,581,1,"单选题","编制压路机台班使用定额时，属于必须消耗的时间的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工组织不好引起的停工时间",false,{"key":16,"text":17,"correct":18},"B","压路机在工作区末端调头时间",true,{"key":20,"text":21,"correct":14},"C","压路机操作人员擅离岗位引起的停工时间",{"key":23,"text":24,"correct":14},"D","暴雨时压路机的停工时间","施工组织不好引起的停工时间，属于损失时间。故A错误；工作区末端的调头时间，属于不可避免的无负荷工作时间，为必须消耗的时间。故 B选项正确。压路机操作人员擅离岗位引起的停工时间属于损失时间。故C错误；暴雨时压路机的停工时间，属于损失时间。故D错误。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]