[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896648":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},896648,581,1,"单选题","通过对施工过程的具体活动进行实地观察，详细记录工人和机械的工作时间消耗、完成产品数量及有关影响因素,再对所获得的资料进行分析，制定出人工定额的方法是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","统计分析法",false,{"key":16,"text":17,"correct":14},"B","比较类推法",{"key":19,"text":20,"correct":21},"C","技术测定法",true,{"key":23,"text":24,"correct":14},"D","经验估计法","技术测定法是根据生产技术和施工组织条件，对施工过程中各工序采用测时法、写实记录法、工作日写实法，测出各工序的工时消耗等资料，再对所获得的资料进行科学的分析，制定出人工定额的方法。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]